Arguments highlight that a fully permitted project cannot be rejected retroactively and that doing so would send a chilling effect to businesses considering moving to Maine
Attorneys on behalf of the New England Clean Energy Connect (NECEC) and Avangrid Networks, a subsidiary of AVANGRID, Inc. (NYSE: AGR), along with Hydro-Quebec made the case today in oral arguments before the Maine Supreme Court that the referendum blocking construction of the NECEC clean energy project is unconstitutional, unfair and short-sighted. The court ruled a previous referendum proposed in 2020 with the exact same purpose of blocking the project was unconstitutional and it was removed from the ballot.
NECEC Transmission LLC, and Avangrid Networks urged the Court to look at the referendum as retroactively applied to the NECEC and find it unconstitutional, citing the constitutional protections for vested rights and the bedrock principle of separation of powers as the key arguments.
“This is a clean energy project that will catapult Maine and New England into a clean and affordable energy future at a time when we are seeing exponential increases in energy costs related to fossil fuels and supply constraints,” said Thorn Dickinson, president & CEO of NECEC Transmission. “The NECEC project received every local, state and federal permit required and substantial construction has been completed. This establishes a so-called ‘vested right’ that cannot be taken away. Retroactively revoking these permits—after substantial construction has been done – violates the Maine Constitution.”
The referendum also violates the Maine Constitution’s strict separation of powers by giving one branch, the legislature, the power to retroactively invalidate final actions by the executive and judicial branches. Accordingly, when the legislature exercises a power committed to another branch of government, the judiciary is not only permitted but compelled to sit in judgment upon such acts, and to pronounce them invalid.
Supporters of the project agree construction of the corridor will be a benefit to Mainers and that the referendum goes too far. Amicus briefs challenging the constitutionality of the referendum were filed in April by nine parties representing a diverse set of stakeholders - from professors of energy and law, environmentalists, local municipalities, public policy leaders, former Maine Public Utilities Commission members, and Maine legislators – demonstrating how this project furthers not only state, regional and national clean energy goals, but also affects the pocketbooks of Mainers.
“This project will provide significant benefits to the local Maine economy including more than 1000 direct jobs and more than $500 million of incremental Gross Domestic Product for Maine during the construction phase,” said Tim Burgess of IBEW Local Union 104.
“NECEC will deliver an abundant supply of low-cost renewable energy to the region that will help us meet our carbon reduction goals,” said Maine’s Public Advocate William Harwood. “We will also get more than $250 million in benefits for Maine citizens and energy customers in the form of economic development and ratepayer relief.”
Tony Buxton, counsel for the Industrial Energy Consumers Group, says the referendum sets a bad precedent. "You can't run a society by referendum. Why don't we change the sign in Kittery from 'Welcome Home' to 'Maine: Where permits mean nothing and referenda are every Tuesday.'”
Opponents of the project were supported by fossil fuel generators and preyed on the emotions of Mainers to make their case. Fossil fuel generator, NextEra Energy and the country’s largest energy climate polluter Vistra, took the lead opposing the project, challenging the project before multiple regulators (and losing before each) providing more than $20 million in dark money to NECEC opponents. According to Climate Action 100+, NextEra is the only Climate Action 100+ U.S.-based utility company with substantial emissions to have not committed to achieving net zero emissions by 2050. The Sierra Club identifies Vistra as the #1 emitter of climate warming pollution in the US power sector.
“The opposition to this project was never about protecting Maine’s woods for NextEra and other fossil fuel companies. It was about protecting their fossil fuel-driven bottom line,” said Dickinson.
"The energy prices they are charging Mainers this year are almost twice as high as the price for the energy that the NECEC will deliver, and prices, and profits of these fossil fuel companies, are expected to be as high or even higher in 2023.”
The Maine Supreme Court is expected to deliver a decision on the injunction against construction later this summer with a ruling on the overall case to follow.
Separate proceedings were also held today regarding the Bureau of Public Lands lease related to the project where NECEC was joined by the State of Maine in arguing that the one mile of land leased from the state where the transmission line would cross does not represent new use since transmission lines already cross that land and therefore does not require legislative approval.
About NECEC Project: The New England Clean Energy Connect (NECEC) Clean Energy Corridor is a $1.2 billion investment that will deliver 1,200 megawatts of renewable hydropower to the New England energy grid in Lewiston, Maine. All of the costs will be paid for by Massachusetts electric customers. Once built, the NECEC will be New England’s largest source of renewable energy, representing a fundamental shift away from fossil fuels while simultaneously lowering energy costs in Maine and New England.
The 145-mile transmission line is being built on land owned or controlled by Central Maine Power. The 53 miles of new corridor on working forest land uses a new clearing technique of tapered vegetation; the remaining two-thirds of the project follows existing power lines created for the state’s hydroelectric industry almost a century ago. Prior to the halt of construction in 2021 due to the legal proceedings, 78 of 832 monopoles have been installed and materials for the project’s construction, including poles and wires, are being stored near the construction site and ready for installation should the court decide to lift the injunction on construction.
Construction is expected to be completed and the line in service by the end of 2024. The project will create more than 1,600 good-paying jobs during the two-and-a-half-year construction period, provide $200 million in upgrades to Maine’s energy grid, making Maine’s electricity service more reliable. The NECEC will allow more producers of renewable energy here in Maine to get their energy on the grid, and because the corridor project will use clean hydropower, it will reduce the use of fossil fuels, cutting three million metric tons of dirty emissions each year.
The NECEC will also deliver significant economic benefits to Maine and the region, including lower electricity prices, increased local real estate taxes and reduced energy costs, expanded fiber optic cable for broadband service in Somerset and Franklin counties and funding of economic development for Western Maine.
For more information about the New England Clean Energy Connect, please visit our website at https://www.necleanenergyconnect.org/.
About AVANGRID: AVANGRID, Inc. (NYSE: AGR) aspires to be the leading sustainable energy company in the United States. Headquartered in Orange, CT with approximately $40 billion in assets and operations in 24 U.S. states, AVANGRID has two primary lines of business: Avangrid Networks and Avangrid Renewables. Avangrid Networks owns and operates eight electric and natural gas utilities, serving more than 3.3 million customers in New York and New England. Avangrid Renewables owns and operates a portfolio of renewable energy generation facilities across the United States. AVANGRID employs approximately 7,000 people and has been recognized by JUST Capital in 2021 and 2022 as one of the JUST 100 companies – a ranking of America’s best corporate citizens. In 2022, AVANGRID ranked second within the utility sector for its commitment to the environment and the communities it serves. The company supports the U.N.’s Sustainable Development Goals and was named among the World’s Most Ethical Companies in 2022 for the fourth consecutive year by the Ethisphere Institute. For more information, visit www.avangrid.com.
View source version on businesswire.com: https://www.businesswire.com/news/home/20220510006389/en/
Contacts
MEDIA
Ted Varipatis
Ted@serrapublicaffairs.com
207-615-4182
Sarah Warren
Sarah.warren@avangrid.com
585-794-9253